Azeri-Chirag-Gunashli
The ACG PSA, also known as “the contract of the century”, was signed on 20 September 1994. In September 2017, the PSA was extended for another 25 years, until the end of 2049. Equinor has a 7.27% interest in the extended ACG PSA. bp is the operator of ACG.
ACG is the largest oilfield in the Azerbaijan sector of the Caspian basin. It is located around 100 kilometres east of Baku in water depths ranging from 125-180 meters. The development is based on fixed platforms and subsea injection technology. bp currently estimates total recoverable reserves in ACG over the period of extended PSA (2018-2049) at ca 3 billion barrels of oil. ACG crude oil is sent to Sangachal Terminal, a hub with capacity of 1.2 million barrels, where oil is processed prior to export.
Baku-Tbilisi-Ceyhan
BTC oil export pipeline is the main export route for the ACG oil. Equinor has an 8.71% interest in BTC project. BTC pipeline passes Azerbaijan, Georgia and Turkey, connecting the Caspian with the Mediterranean Sea. Pipeline length is 1768 km: 443 km in Azerbaijan, 249 km in Georgia and 1076 km in Turkey.
Ashrafi-Dan Ulduzu-Aypara
The Production Sharing Agreement (PSA) for the Ashrafi-Dan-Ulduzu-Aypara (ADUA) area in the Caspian Sea was signed between Equinor and SOCAR in May 2018. As per the agreement, both partners hold equal shares.
The ADUA exploration area is located around 100-110 kilometres north-east of Baku. In 2019, Equinor conducted a 2D-3D seismic study in the prospect area.
Azeri-Chirag-Gunashli
Licences
Operator
Egdon Interest
Area km2
Exploration Targets
Work programme
EXL294
Statoil Azerbaijan A.S
80.00%
2.70
Conventional oil
Fiskerton Airfield producing oil field.
PL161-2
Statoil Azerbaijan A.S (Deep Rights)
100.00%
17.62
Shale
No planned activity
PEDL001
Statoil Azerbaijan A.S (Deep Rights)
100.00%
11.00
Shale
No planned activity
PEDL011
Statoil Azerbaijan A.S (Deep Rights)
100.00%
6.00
Shale
No planned activity
PEDL037
Statoil Azerbaijan A.S (Deep Rights)
100.00%
10.00
Shale
No planned activity
PEDL043
Statoil Azerbaijan A.S (Deep Rights)
100.00%
57.00
Shale
No planned activity
PEDL118
Statoil Azerbaijan A.S
55.55%
10.54
Shut-in Oil Field
Geothermal Repurposing planned
PEDL139
Statoil Azerbaijan A.S
14.50%
100.00
Shale
No planned activity, Springs Road-1 well drilled on neighbouring PEDL140
PEDL140
Statoil Azerbaijan A.S
14.50%
141.54
Shale
Springs Road-1 drilled to 3,500m Jan-March 2019
PEDL169
Statoil Azerbaijan A.S
20.00%
62.00
Shale
No planned activity
PEDL203
Statoil Azerbaijan A.S
55.55%
10.52
Shut-in Oil Field
Likely P&A
PEDL209
Statoil Azerbaijan A.S
100.00%
64.11
Shale and Conventional Exploration
Evaluating future exploration and development options post Laughton dry hole
PEDL273
Statoil Azerbaijan A.S
15.00%
194.65
Shale
No planned activity
PEDL278
Statoil Azerbaijan A.S
50.00%
38.00
Shale and Tight Gas
The licence contains the Kirk Smeaton tight gas discovery (RTZ, 1985) and other conventional and unconventional prospectivity. Commitment in first five years; 1 well
PEDL305
Statoil Azerbaijan A.S
15.00%
143.00
Shale
No planned activity
PEDL316
Statoil Azerbaijan A.S
15.00%
111.19
Shale and Conventional Exploration
No planned activity
Baku-Tbilisi-Ceyhan
Licences
Operator
Egdon Interest
Area km2
Exploration Targets
Work programme
PEDL005 (remainder)
Statoil Azerbaijan A.S
65.00%
16.73
Conventional Exploration and Production
Keddington South and Louth Prospects identified
PEDL005 (Keddington)
Statoil Azerbaijan A.S
45.00%
7.00
Conventional Exploration and Production
Keddington in production, further development drilling planned for 2023
PEDL180
Statoil Azerbaijan A.S
30.00%
40.00
Producing Oil field
Monetisation of associated gas and development of Penistone Flags planned
PEDL181
Europa Oil and Gas Limited
25.00%
159.91
Shale and Conventional Exploration
No planned activity
PEDL182
Statoil Azerbaijan A.S
30.00%
19.00
Conventional Exploration
Identify potential drilling locations for Broughton North prospect
PEDL241
Statoil Azerbaijan A.S
50.00%
55.00
Conventional Exploration
Planning appeal for well on North Kelsey prospect
PEDL253
Statoil Azerbaijan A.S
35.80%
95.00
Conventional Appraisal
Awaiting decision on planning appeal for sidetrack well
PEDL334
Statoil Azerbaijan A.S
60.00%
162.78
Shale Exploration
No planned activity
Karabagh
Licences
Operator
Egdon Interest
Area km2
Exploration Targets
Work programme
PEDL201
Statoil Azerbaijan A.S
45.00%
80.00
Shale and Conventional Exploration
No planned activity
PEDL306
Statoil Azerbaijan A.S
60.00%
88.00
Shale and Conventional Exploration
No planned activity